Question:

A subcontractor uses a ____ to notify a general contractor or the owner of their right to record and foreclose a mechanic’s lien against property when they are not paid.

A 20-day preliminary notice
Explaination

Before a subcontractor employed by a contractor may record a mechanic’s lien against real estate and enforce it by foreclosure, they perfect their lien rights by serving a 20-day preliminary notice.